How Long Do Building Permits Take in Broward and Miami-Dade?

By Scott Rosenberg, licensed GC5 min read

The short answer

Florida Statute 553.792 gives building departments set deadlines once they have a complete application: 5 business days for work under $15,000 on an existing single-family home, 30 business days for residential units under 7,500 square feet, and 60 business days for larger homes, multifamily buildings up to 50 units and nonresidential buildings under 25,000 square feet. The department must flag missing information within 5 business days, and if it misses a deadline without sending a deficiency notice, the permit fee drops 10 percent for each business day late. Real timelines are usually longer because of corrections, and because zoning, HOA, flood, historic or coastal approvals happen before or alongside the permit.

"How long will the permit take?" is one of the first questions every homeowner asks, and the honest answer used to be "it depends." It still depends, but Florida law now puts real limits on how long a building department can sit on a complete application, and it gives you money back when they miss them.

Here are the deadlines, how they work in practice, and the things that actually slow permits down in Broward and Miami-Dade.

The state deadlines

Review deadlines under Florida Statute 553.792 (after a complete application)
Type of projectDeadline to approve or deny
Work valued under $15,000 on an existing single-family home (structural, electrical, plumbing, roofing and similar)5 business days
Residential units, including single-family homes, under 7,500 square feet30 business days
Residential units of 7,500 square feet or more60 business days
Nonresidential buildings under 25,000 square feet, and signs60 business days
Multifamily buildings up to 50 units; site plans and plats that need no public hearing; lot grading60 business days
Local governments can set shorter deadlines. The statute does not set one for nonresidential buildings of 25,000 square feet or more or for multifamily buildings over 50 units. Applicants can waive the deadlines in writing.

When the clock starts, and what stops it

  1. Completeness check. Within 5 business days of receiving your application, the department must tell you in writing what is missing under its published requirements. If it does not, the application is treated as complete.
  2. Review. The deadline for your project type runs from a complete application.
  3. Deficiency notice. If the reviewers find code problems, they send a written notice listing them before the deadline. You then have 10 business days to submit corrections, or the application can be denied.
  4. Resubmittal. After you resubmit on time, the department has 10 business days to approve or deny.

Why real timelines run longer

The statute covers the building department's review. Most of the delay we see comes from everything around it:

  • Incomplete drawings. Every round of corrections adds time on both sides. Complete, coordinated drawings are the single best way to speed up a permit.
  • Zoning review. Setbacks, lot coverage and parking are checked by zoning, often before or alongside building review.
  • HOA and condo approvals. These run separately. Since July 2026, an HOA cannot require a permit before it reviews your plans, which lets both move together; our post on HOA approval explains.
  • Design and historic boards. Cities like Coral Gables require design approval before the permit.
  • Flood zones. Elevation certificates and substantial improvement reviews add steps for older homes in flood zones.
  • Beachfront property. Work seaward of the Coastal Construction Control Line needs a state permit as well.
  • Product approvals. Windows, doors and roofing in the High-Velocity Hurricane Zone need current Miami-Dade NOAs, and an expired or missing approval stops review.

Private providers

Florida lets the owner, or the contractor with the owner's written authorization, hire a licensed private provider for plan review, inspections or both under Florida Statute 553.791. When a private provider does the plan review, the building department must flag incomplete forms within 10 business days, or 5 business days for a single-trade review on a one- or two-family home, or the permit is considered approved. The department also has to reduce its fees for the work it no longer does. It adds a cost of its own, so it makes the most sense on larger or time-sensitive projects.

Small jobs

Some small jobs no longer need a permit at all. Since July 1, 2026, single-family homeowners can ask for an exemption for certain work under $7,500, with important exceptions such as flood zones and electrical, plumbing, structural, mechanical and gas work. Our permit guide explains what qualifies.

How to get a permit faster

  • Submit complete, coordinated drawings with every product approval attached.
  • Answer the completeness and deficiency notices quickly; your response time counts against your schedule, not theirs.
  • Start HOA, design board and other approvals early so they are not waiting on each other.
  • Use a contractor who pulls permits in your city regularly and knows its reviewers' common comments.

The bottom line

Florida's deadlines put a ceiling on building department review: 5, 30 or 60 business days depending on the project, with refunds when they are missed. The total time from idea to permit depends mostly on how complete your drawings are and how many other approvals the property needs. We pull permits across Broward, Miami-Dade and Palm Beach for remodels, additions and new homes, and we plan the approvals into the schedule from the start. Tell us about your project.

Quick questions

How long does a building permit take in Florida?
Once the application is complete, Florida Statute 553.792 gives building departments 5 business days for work under $15,000 on an existing single-family home, 30 business days for residential units under 7,500 square feet, and 60 business days for larger homes, multifamily up to 50 units and nonresidential buildings under 25,000 square feet. Corrections and other approvals usually add time.
What happens if the building department misses the deadline?
Unless it sent a timely deficiency notice or another exception applies, the permit fee is reduced by 10 percent of the original fee for each business day the initial deadline is missed, and by 20 percent per business day if it misses the 10-day deadline after a resubmittal.
When does the permit review clock start?
When the application is complete. The department has 5 business days to tell you in writing what is missing; if it does not, the application is treated as complete.
Can a private provider speed up my permit?
Often. Under Florida Statute 553.791, an owner or authorized contractor can hire a licensed private provider for plan review and inspections. The building department then has short deadlines to flag incomplete forms, or the permit is considered approved, and it must reduce its fees.
Why is my permit taking longer than the state deadline?
Usually because of corrections, or because other approvals come first or run alongside: zoning, HOA or condo approval, design or historic boards, flood zone reviews, or a state coastal permit near the beach.

Sources

This article is general information, not legal advice. Building departments in Miami-Dade, Broward and Palm Beach counties set their own procedures, so confirm the requirements for your property with your local building department.

Scott Rosenberg

Florida Certified General Contractor, CGC1541479

Scott qualifies Rosemont Ventures Group LLC and has worked in general contracting since 1998. He writes Building Blocks to answer the questions South Florida owners ask before they build. Verify the license.

Free estimate

Tell us what you want to build

Send a few details and a licensed contractor will call you back, usually within one business day. We'll talk through scope, permits and a realistic budget range. No pressure and no obligation.

Request a callback