Permit Drawings in South Florida: Do You Need an Architect or an Engineer, and What Goes Into a Permit Set?

By Scott Rosenberg, licensed GC7 min read

The short answer

Florida law doesn't require an architect to design a one- or two-family home or a townhouse, regardless of cost, under section 481.229. Structural work is different: beams, new openings in bearing walls, additions, second stories and new homes need drawings and calculations from a Florida-licensed engineer or architect, and South Florida building departments expect them signed and sealed, usually digitally. Small electrical, plumbing and mechanical work can be laid out by the licensed trade contractor, while larger systems need an engineer. A typical permit set for an addition or a new home includes a signed and sealed survey, architectural, structural, electrical, plumbing and mechanical plans, energy calculations and product approvals for windows, doors and roofing, and in a flood zone an elevation certificate. Once the application is complete, Florida law gives the building department deadlines to approve or deny it, starting at 5 business days for small jobs on an existing home.

Nobody posts their permit drawings on Instagram. But on almost every project we take over from someone else, the delay started in the same place: plans drawn by the wrong person, drawn without enough detail, or drawn before anyone checked what the building department actually wanted. The construction is usually the predictable part. The paperwork is where weeks disappear.

Here is who has to draw what in Florida, what goes into a permit set in South Florida, and how to keep the review from dragging on.

Who has to draw and seal your plans

Who prepares each part of a permit set for a South Florida house
Part of the setWho prepares itNotes
Architectural plans (floor plans, elevations, sections)An architect, or anyone allowed to design homes under Florida lawSection 481.229 exempts one- and two-family homes, townhouses and their outbuildings from the architect requirement, regardless of cost. Many owners still hire an architect for the design itself.
Structural plans and calculationsA Florida-licensed professional engineer or registered architectNeeded for additions, second stories, new homes, new or enlarged openings in bearing walls, beams and slabs. Expect them to be signed and sealed.
Electrical, plumbing and mechanical plansThe licensed trade contractor for smaller systems; an engineer for larger onesFlorida guidance sets engineer thresholds around 600 amps of electrical service, 250 plumbing fixture units and 15 tons of cooling, with dollar limits on plumbing and mechanical work.
SurveyA Florida-licensed surveyorA signed and sealed boundary or topographic survey; in a flood zone it should show the flood zone and elevations.
Energy calculationsThe designer or an energy raterRequired for additions and new homes to show the project meets the Florida energy code.
Product approvalsThe manufacturer, collected by the contractorEvery window, door, shutter and roofing product needs a Miami-Dade NOA or an HVHZ-approved Florida approval in Miami-Dade and Broward. Our NOA lookup guide shows how to check one.
Based on Florida Statutes section 481.229 and Florida building department guidance on signed and sealed documents. Your building official decides what a specific project needs, so check the city's checklist before drawings start.

What goes into a permit set

Each city has its own checklist, but they look alike across Miami-Dade and Broward. Miami Beach's residential addition checklist is a good example of a full set. It asks for digitally signed and sealed drawings, a signed and sealed site survey, architectural, structural, electrical, mechanical and plumbing plans and a tree survey, and, when they apply, structural calculations, an as-built elevation certificate for the existing building, a geotechnical report, special inspector forms, product approvals, cooling load calculations and an energy calculation form, along with drainage calculations and zoning data.

In Miami-Dade, a new home or addition can also need county approvals beyond the city, such as DERM environmental reviews and water and sewer sign-offs. In Broward, some cities route certain projects to a drainage district or to county environmental review first. Our South Florida building permits guide links to the local guide for each city we've covered.

What different projects usually need

Typical drawings by project type in South Florida
ProjectWhat the permit usually needs
Kitchen or bathroom remodel, no walls movedTrade permits for the electrical, plumbing and mechanical work, with simple layouts. Some cities want a floor plan and a cabinet or fixture layout.
Removing or opening a wallIf the wall is load-bearing, a structural engineer's design for the beam and its supports. Don't guess; in a concrete block house, many interior walls carry the roof.
Window and door replacementA window and door schedule with sizes, the product approvals and, for new or larger openings, structural details for the opening.
ReroofThe roofing permit application, product approvals for each layer of the roof system and, on some homes, roof-to-wall connection paperwork.
Room addition or second storyA full signed and sealed set: survey, architectural, structural with calculations, electrical, plumbing, mechanical, energy, and flood information if the lot is in a flood zone. See our second-story addition guide.
New homeEverything above, plus site, drainage and utility approvals, and in Miami-Dade the county environmental and water and sewer reviews. Our guide to how long it takes to build a house covers the schedule.
General guidance. Requirements vary by city and change from time to time, so download the current checklist for your project.

How long plan review takes

Once an application is complete, Florida Statute 553.792 gives building departments deadlines: 5 business days for work under $15,000 on an existing single-family home, 30 business days for residential units under 7,500 square feet, and 60 business days for larger homes and many other buildings. The department has to flag missing information within 5 business days, and after you resubmit, it has 10 business days to approve or deny. If it misses those deadlines without the required notices, the permit fee goes down.

Florida also lets an owner, or a contractor with the owner's written permission, hire a licensed private provider for plan review, inspections or both under section 553.791. On the right project, that can save weeks. Our post on how long building permits take goes through the details.

  • Start with the checklist. Get the city's current checklist for your exact project before anyone starts drawing.
  • Answer comments fast. The time you take to respond counts against your schedule, not the department's.
  • Pick products early. Windows, doors and roofing need approvals in the set, and a late product change means a revision.
  • Mind the code date. Applications filed from December 31, 2026 fall under the 2026 Florida Building Code, so plans drawn to the current code should be submitted before your department's cutoff.

Permit expediters, owner-builders and who signs the permit

A permit expediter handles the running around: assembling the package, submitting it, tracking reviews and chasing comments. That can be useful, but an expediter isn't a contractor. The permit itself is pulled by the licensed contractor who will do the work, or by the owner as an owner-builder, and whoever signs it is responsible for the job passing inspection. Florida takes misuse of a contractor's license seriously; our demolition division explains the risks of rented licenses and permit expediters.

If a contractor asks you to pull an owner-builder permit for work they're doing, that's a red flag: it puts the legal responsibility, and often the liability for unlicensed work, on you. Our guide to hiring a general contractor lists the other warning signs.

How we handle drawings and permits

On our projects, we coordinate the architect, engineer and surveyor or work from the plans you already have, check the set against the city's checklist before it goes in, submit under our license and answer every comment. It's step five of how we work. If you're not sure what your project needs, a site visit usually settles it.

The bottom line

For a house in Florida, you don't need an architect by law, but you do need a licensed engineer or architect for anything structural, and South Florida departments expect a complete, signed and sealed set. Start from the city's checklist, choose your products early and answer review comments quickly. We handle additions, new homes, renovations and structural repairs from drawings to final inspection across Miami-Dade, Broward and Palm Beach. Tell us about your project.

Quick questions

Do I need an architect to build or remodel a house in Florida?
Not by law. Florida Statute 481.229 exempts one- and two-family homes, townhouses and their outbuildings from the architect requirement, regardless of cost. Structural work still needs a Florida-licensed engineer or architect, and many owners hire an architect for the design anyway.
Do I need an engineer to remove a wall?
If the wall is load-bearing, yes. The beam and its supports need a structural design from a Florida-licensed engineer or architect, and the building department will expect it in the permit set. In concrete block houses, many interior walls carry the roof, so don't assume.
What does signed and sealed mean?
It means a Florida-licensed architect, engineer or surveyor has applied their professional seal and signature to the drawings, taking professional responsibility for them. Most South Florida building departments accept digital signatures and seals on electronic submittals.
What documents do I need for a home addition permit?
Usually a signed and sealed survey; architectural, structural, electrical, plumbing and mechanical plans; structural and energy calculations; product approvals for windows, doors and roofing; and in a flood zone, an elevation certificate. Cities add their own items, so get the current checklist.
How long does plan review take in South Florida?
Once the application is complete, Florida law sets deadlines starting at 5 business days for work under $15,000 on an existing single-family home and 30 business days for homes under 7,500 square feet. The department must flag missing items within 5 business days and has 10 business days to act after a resubmittal.
Can a permit expediter pull my permit?
No. An expediter can prepare, submit and track the paperwork, but the permit is pulled by the licensed contractor doing the work, or by the owner as an owner-builder, and that person is responsible for the job.

Sources

This article is general information, not legal advice. Building departments in Miami-Dade, Broward and Palm Beach counties set their own procedures, so confirm the requirements for your property with your local building department.

Scott Rosenberg

Florida Certified General Contractor, CGC1541479

Scott qualifies Rosemont Ventures Group LLC and has worked in general contracting since 1998. He writes Building Blocks to answer the questions South Florida owners ask before they build. Verify the license.

Free estimate

Tell us what you want to build

Send a few details and a licensed contractor will call you back, usually within one business day. We'll talk through scope, permits and a realistic budget range. No pressure and no obligation.

Request a callback