Florida Building Code 9th Edition (2026): What Changes on December 31 and How to Get Your Permit Under the Current Code

By Scott Rosenberg, licensed GC7 min read

The short answer

The Florida Building Code, 9th Edition (2026), takes effect statewide on December 31, 2026. In Miami-Dade, the county says every permit application and set of plans submitted on or after that date has to comply with the new edition, and anything sent through the online portal after 4 PM on December 30, 2026 counts as submitted under the new code. Applications filed before the cutoff are reviewed under the current 8th Edition. If yours expires later, Miami-Dade will only extend it on a written request made within 180 days showing it wasn't abandoned; otherwise you start over under the 2026 code. Broward and Palm Beach cities set their own procedures, so confirm the cutoff with your building department. If you're designing a project now, the practical question is whether you can submit a complete application before the end of December.

Florida updates its building code every three years. The current edition, the 8th (2023), has been in force since December 31, 2023. The 9th Edition takes over on December 31, 2026. For most homeowners that's background noise. For anyone in the middle of designing a new home, an addition, a remodel or a commercial build-out, it's a deadline that can decide which set of rules the whole project is built to.

Here is what the change means in South Florida, what we know about what's different, and how to plan around it.

Which code will my project fall under?

What counts is when the permit application is submitted, not when the work starts. Miami-Dade's Permitting and Inspection Center has spelled out its rules for this change:

  • On or after December 31, 2026: all permit applications and plans have to comply with the new 2026 edition.
  • The online cutoff is earlier: anything submitted through the county's online portal after the close of business at 4 PM on December 30, 2026 also has to comply with the 2026 edition.
  • Expired applications: an application filed before the cutoff that later expires can be extended only if you ask in writing, within 180 days of the expiration, and show it wasn't abandoned and was being pursued in good faith. If that request is denied, you need a new process number, upfront fees and plans that meet the 2026 code.
  • Model programs: builders using "cookie cutter" or master model plans are told to start updating them now to avoid delays.

Cities in Broward and Palm Beach run their own building departments and set their own transition procedures. When the last code changed, in 2020, Broward County's building code office used the same pattern: a 4 PM cutoff on December 30, and extensions for expired applications only on a written request within 180 days. Expect something similar, but get the exact rule from the city or county that will issue your permit.

What's changing in the 9th Edition

The Florida Building Commission publishes an analysis of changes for each volume. For the Building volume, the 8th Edition is the base and the 2024 International Building Code is the model, though the Commission notes that not every 2024 change was brought in. Some of the changes listed that matter in South Florida:

Selected changes in the 9th Edition (2026) Florida Building Code, Building
AreaWhat the analysis of changes lists
Wind speed definitionThe definition of ultimate design wind speed is revised so the wind speeds in Section 1609.3 are equivalent to the basic wind speeds in ASCE 7.
Corrosion near the coastNew Section 1403.12 requires fasteners and connectors within 3,000 feet of a saltwater coastline to meet the corrosion resistance requirements of Section 1711.
Water-resistive barriersSection 1404.2 sets lap requirements of 2 inches horizontally and 6 inches at joints for No. 15 felt and ASTM E2556 barriers.
Vinyl sidingNew Section 1404.9.1 requires insulated and backed vinyl siding to be certified to ASTM D7793 and D7445.
Roof flashing and ventilationFlashing rules now cover all roof types and shapes, and roof ventilation is clarified to need both intake and exhaust, with an exception pointing to the rules for unvented attics.
Flood documentationResidential structural plans add base flood elevations and proposed lowest floor elevations, and the final inspection calls for a FEMA Elevation Certificate or equivalent.
Accessibility rampsSection 105.2 adds a permit exemption for accessibility renovations of one- and two-family homes, including ramps with a rise of 48 inches or less.
Digital plansSection 107.1 lets the building official require construction documents in digital form.
From the Florida Building Commission's Analysis of Changes, 9th Edition (2026) Florida Building Code, Building. This is a selection, not the full list, and other volumes (Residential, Existing Building, Energy) have their own analyses. Your designer should check the adopted text at floridabuilding.org for your project.

You may read online that the new code expands where impact protection is required. The definition of the wind-borne debris region has been debated, including a study for the Building Commission that recommended adding inland areas near large bodies of water, but treat any claim about the final 2026 text as a proposal until you see it in the adopted code. Our post on the HVHZ versus the wind-borne debris region explains the current rules. In Miami-Dade and Broward, the High-Velocity Hurricane Zone already requires approved protection on every opening.

Who should pay attention

  • New homes. Plans drawn to the 8th Edition and submitted after the cutoff have to be reviewed, and possibly revised, to the 9th. See our guides to what it costs to build and how long it takes.
  • Additions and major remodels. Anything that needs plan review falls under the code in effect when it's submitted. If you are near the 50 percent threshold in a flood zone, read our post on the 50 percent rule too.
  • Coastal projects. The new corrosion rule for fasteners and connectors within 3,000 feet of saltwater reaches a lot of South Florida, from the barrier islands to neighborhoods along the Intracoastal.
  • Windows, doors and roofs. Check that the products in your plans carry approvals valid under the code your permit falls under. Our guide on how to look up an NOA shows where to find that.
  • Commercial build-outs and condo repairs. Tenant improvements and milestone or recertification repairs that need plans follow the same cutoff. Our posts on commercial build-outs and milestone repairs cover the rest of the process.

What to do in the next eight weeks

  1. Ask your designer where the drawings stand. If the plans can be complete, signed and sealed in time, aim to submit well before the last week of December, not at 3:59 PM on December 30.
  2. Confirm the cutoff with your building department. Miami-Dade's is published. In Broward and Palm Beach, ask the city or county that issues your permit.
  3. Line up the outside approvals. HOA review, a design or historic board, or a drainage district release can delay a submittal. Start those now.
  4. Check the products. Windows, doors, shutters and roofing in the plans need current approvals for the code your permit will fall under.
  5. Track the expiration date after you submit. Answer comments quickly so the application isn't treated as abandoned.
  6. If you can't make it, design to the new code. Starting under the 9th Edition on purpose is better than a half-ready application that expires.

The new code isn't the only date to plan around. Improvements are added to your property tax assessment as of the first January 1 after they're substantially complete, and Amendment 3 changes the homestead exemption starting in 2027. Our post on Amendment 3 and taxes on renovations covers the timing.

The bottom line

On December 31, 2026, the 9th Edition becomes the code for every new permit application in Florida, and in Miami-Dade the online cutoff is 4 PM on December 30. If your plans are nearly ready, a complete submittal before the cutoff keeps your project under the 8th Edition; if not, design to the new code from the start. We pull permits for new homes, additions, renovations and commercial build-outs across Miami-Dade, Broward and Palm Beach. Tell us where your project stands and we'll tell you whether the timing works.

Quick questions

When does the 2026 Florida Building Code take effect?
The Florida Building Code, 9th Edition (2026), takes effect statewide on December 31, 2026. It replaces the 8th Edition (2023), which has been in force since December 31, 2023.
Does the new Florida Building Code apply to my permit?
It depends on when the application is submitted. In Miami-Dade, applications and plans submitted on or after December 31, 2026, or through the online portal after 4 PM on December 30, 2026, have to comply with the 2026 edition. Applications filed before the cutoff are reviewed under the current code. Broward and Palm Beach cities set their own procedures.
What happens if my permit application expires after the code changes?
In Miami-Dade, an application filed before the cutoff that expires can be extended only on a written request made within 180 days of the expiration, showing it was not abandoned and was being pursued in good faith. Otherwise you need a new application, new fees and plans that meet the 2026 code.
What are the main changes in the 9th Edition Florida Building Code?
The Building Commission's analysis lists changes including a revised wind speed definition aligned with ASCE 7, corrosion-resistant fasteners within 3,000 feet of a saltwater coastline, water-resistive barrier lap rules, roof flashing and ventilation clarifications, added flood documentation, and a permit exemption for small accessibility ramps on one- and two-family homes. Check the adopted text for your project.
Should I rush to submit my permit before December 31, 2026?
Only if the plans are genuinely complete. An incomplete application can be rejected, and one that isn't pursued can be treated as abandoned. If your drawings can't be ready in time, it's usually better to design to the new code from the start.

Sources

This article is general information, not legal advice. Building departments in Miami-Dade, Broward and Palm Beach counties set their own procedures, so confirm the requirements for your property with your local building department.

Scott Rosenberg

Florida Certified General Contractor, CGC1541479

Scott qualifies Rosemont Ventures Group LLC and has worked in general contracting since 1998. He writes Building Blocks to answer the questions South Florida owners ask before they build. Verify the license.

Free estimate

Tell us what you want to build

Send a few details and a licensed contractor will call you back, usually within one business day. We'll talk through scope, permits and a realistic budget range. No pressure and no obligation.

Request a callback