The short answer
In Coral Gables, most exterior projects go through the city's Board of Architects before a building permit is issued. The board reviews new homes, building expansions, pools, paving, signs and roof tiles for compatibility of color, materials, windows and proportion, and a typical project gets preliminary and then final approval. Submittals need a tree survey and tree protection plan, and properties on the Coral Gables historic register also need a Certificate of Appropriateness. Plan design time around the board's weekly Thursday meetings before the building department review begins.
Coral Gables was planned in the 1920s around a consistent Mediterranean look, and a century later the city still enforces it. That is a big part of why the neighborhoods look the way they do, and also why projects that would be simple in other cities take an extra step here.
The extra step is the Board of Architects. If you are planning an addition, a new house, a pool, new roof tiles or any change to the outside of a building in Coral Gables, this is how the process works and how to keep it from eating your schedule.
What the Board of Architects reviews
The board decides whether a project meets the design review standards in the city's zoning code, with a focus on the compatibility of color, materials, windows and proportion. The city lists the kinds of work it reviews:
- New residences and new commercial buildings
- All building expansions, which includes home additions
- Pools and pavement, such as driveways and patios
- Roof tiles
- Signs
Interior remodels that do not change the outside of the building generally do not go to the board, though they still need the normal building permits. If you are unsure whether a change counts, the City Architect is available to help applicants work through design questions.
Preliminary and final approval
According to the city, a typical project involves a preliminary and a final board approval before the building permit is issued. In practice:
- Preliminary approval looks at the design concept: massing, style, materials and how the project sits on the lot and with its neighbors. Comments at this stage are much cheaper to address than after construction drawings are done.
- Final approval looks at the developed drawings, including the details, materials and colors that will actually be built.
- Then the permit. With final approval in hand, the project goes through building department plan review like anywhere else.
The board meets every Thursday, so the calendar works in weekly steps. Submittal deadlines come before each meeting, and if comments require changes, the revised design goes back on a later agenda.
What the submittal needs
| Item | Why it matters |
|---|---|
| Board of Architects review application | The city's form that starts the review |
| Tree survey and tree protection plan | Required for submittals to the Development Review Committee and the Board of Architects, and for demolition permits |
| Architectural drawings | Site plan, elevations and details showing how the project fits the design standards |
| Materials and colors | The city publishes pre-approved exterior paint palettes from major paint brands, and roof tiles are reviewed specifically |
If the house is historic
Coral Gables has its own historic register. Properties that are designated landmarks, or that sit in a designated historic district, need a Certificate of Appropriateness before most exterior work and before a building permit or variance. Minor work such as reroofing, painting or in-kind repairs is generally handled by city staff, while additions, demolitions and major exterior changes go to the Historic Preservation Board at a public hearing. Check whether your property is on the register before you design anything.
How to plan the schedule
- Start with the survey and the rules. Tree survey, property survey, zoning limits and, if it applies, historic status.
- Design to the standards from day one. Mediterranean-compatible massing, materials and colors from the approved palettes save rounds of comments.
- Build in board time. Preliminary and final approval each depend on getting onto a Thursday agenda, plus time for revisions.
- Then permit time. Building department review starts after board approval. Our post on how long building permits take explains the state deadlines.
- Build what was approved. Changes during construction that affect the exterior, such as a different window, tile or color, can need a new approval. Settle selections before the final submittal.
Where the contractor fits
The architect leads the board submittals, but a contractor who knows the process helps in two ways: pricing the design early so the approved version is one you can afford, and building exactly what the board approved, down to the tile and the trim. We work with your architect through approval and then pull the permit. Our post on hiring a general contractor covers what to check first.
The bottom line
In Coral Gables, design approval comes before the permit, and it shapes the project more than in most cities. Get the tree survey and historic status early, design to the city's standards from the start, and plan for weekly board meetings in your timeline. We build additions, new homes and whole-home renovations in Coral Gables and across Miami-Dade. Tell us about your project.
Quick questions
- Do I need Board of Architects approval in Coral Gables?
- For most exterior work, yes. The board reviews new residences, building expansions such as additions, pools, pavement, signs and roof tiles before a building permit is issued. Interior work that does not change the outside generally does not go to the board.
- How often does the Coral Gables Board of Architects meet?
- The city says the board meets every Thursday. A typical project needs a preliminary and a final approval, so plan for more than one meeting plus time for any revisions.
- Does Coral Gables require a tree survey?
- Yes. The city requires a tree survey and tree protection plan for submittals to the Development Review Committee and the Board of Architects, and for demolition permits.
- Can I pick any paint color for my house in Coral Gables?
- Exterior colors are part of design review. The city publishes pre-approved exterior paint palettes, and choosing from them makes approval simpler.
- What if my Coral Gables house is historic?
- Designated landmarks and properties in designated historic districts need a Certificate of Appropriateness before most exterior work. Minor work is usually handled by staff, while additions and major changes go to the Historic Preservation Board at a public hearing.
Sources
- City of Coral Gables, Board of Architects
- City of Coral Gables, Preserving Our Past (historic preservation guide)
This article is general information, not legal advice. Building departments in Miami-Dade, Broward and Palm Beach counties set their own procedures, so confirm the requirements for your property with your local building department.

Scott Rosenberg
Florida Certified General Contractor, CGC1541479
Scott qualifies Rosemont Ventures Group LLC and has worked in general contracting since 1998. He writes Building Blocks to answer the questions South Florida owners ask before they build. Verify the license.