Condos & Commercial

Remodeling a Condo Unit in Florida: Association Approval, Permits and Building Rules

By Scott Rosenberg, licensed GC5 min read

The short answer

In a Florida condo, you usually need two approvals for a remodel: the association's, under your declaration and rules, and the city's building permit for anything beyond cosmetic work. Florida law bars owners from doing anything that affects the safety or soundness of the building and limits changes to common elements, while associations must adopt hurricane protection specifications and cannot refuse windows or shutters that meet them. Day to day, the building's rules on insurance, work hours, elevators, flooring and noise drive the schedule as much as the construction does.

Remodeling a condo looks smaller than remodeling a house. Fewer square feet, no roof, no yard. In practice it often takes more planning, because you are working inside a shared building with neighbors on every side, a board to answer to, and a management office that controls the elevator.

This guide covers what the association can and cannot control, what needs a permit, and the building rules that decide how fast the job goes. It is about condominiums. Single-family and townhouse communities with an HOA follow a different statute, covered in our post on HOA approval and building permits.

Two approvals, often in a set order

The association approves the project under the condominium's declaration and rules. The city or county building department approves the construction through a permit. The 2026 change that stops HOAs from requiring a permit before they review plans is in the HOA statute; Florida's condominium statute has no matching rule. Building departments may require proof of association approval before they issue one. Broward's Board of Rules and Appeals has said municipalities may do exactly that. Plan on getting association approval early, because the permit may depend on it.

What Florida law says

  • Safety and soundness. Section 718.113 says an owner may not do anything inside the unit or on the common elements that would adversely affect the safety or soundness of the common elements or association property. Structural walls, slabs and columns belong to the building as a whole.
  • Common elements are not yours to change. Material alterations to common elements need the procedure in your declaration or, if it has none, approval by 75 percent of the voting interests. Moving a wall into a hallway or enclosing part of a common area is not a unit remodel.
  • Hurricane protection. Every residential condo board must adopt hurricane protection specifications for each building, covering things like color and style within the building code. The board cannot refuse an owner's installation or replacement that conforms to them, though it can require a uniform exterior look.
  • Everything else comes from your documents. Most rules about remodeling, such as approval forms, deposits, contractor requirements and flooring, are in the declaration, bylaws and rules adopted by the board. Ask management for the current versions before you design anything.

What needs a city permit

Common condo remodel items and permits
WorkPermit usually needed?Notes
Paint, cabinets and counters in the same layoutUsually noThe association may still want notice and work hours followed
New flooringUsually noMany buildings require approved sound underlayment and inspect it before the finish goes down
Moving or adding plumbing fixturesYesRisers and shared drain lines often need association coordination and a water shutoff
Electrical changes, new circuits or a new panelYesPlan for the building's electrical room and shutoff procedures
Removing or moving interior wallsYesAn engineer must confirm the wall is not structural
Windows and sliding doorsYesProducts must meet the building's specifications and, in Miami-Dade and Broward, High-Velocity Hurricane Zone approvals
Drilling or cutting the concrete slabYes, with engineeringMany towers have post-tensioned slabs with steel cables under tension; the slab must be scanned and the work engineered
Check your building department; rules differ by city. The 2026 state permit exemption for small jobs applies to single-family homes, not condo units.

The building rules that set your schedule

  • Insurance certificates. Most associations want the contractor's general liability and workers' compensation certificates, often naming the association, before anyone starts.
  • Work hours. Weekday-only windows with quiet hours are common, and some buildings restrict noisy work further in season.
  • Elevators and loading. Expect to reserve the service elevator, pad it, and use a set loading area. Debris usually has to leave the same way.
  • Deposits and inspections. Many buildings take a damage deposit and inspect the common areas before and after the job.
  • Sound control. Hard flooring over another unit often needs approved underlayment, and the building may want to see it before the finish floor goes in.
  • Shutoffs. Plumbing and electrical work that needs a riser or building shutoff has to be scheduled with management and noticed to neighbors.

The order that works

  1. Get the declaration, rules, remodeling packet and hurricane protection specifications from management.
  2. Design within those rules, and have an engineer review anything that touches walls, slabs or shared systems.
  3. Submit to the association with drawings, product information and contractor documents.
  4. Apply for the city permit, with proof of association approval if your building department asks for it.
  5. Schedule elevators, shutoffs and deliveries with management, and notify neighbors.
  6. Build, pass inspections, and close out with the association, including the deposit.

The bottom line

A condo remodel succeeds or fails on paperwork and coordination as much as on carpentry. Read the building's rules first, keep structural and shared systems in an engineer's hands, and give the association and the building department matching drawings. We handle kitchen and bathroom remodels, impact windows and sliders and full unit renovations in condo buildings across Miami-Dade, Broward and Palm Beach, including the association submittals and permits. Tell us about your unit.

Quick questions

Do I need association approval to remodel my condo in Florida?
Usually, yes. Remodeling rules come from your declaration and the rules the board adopts, and most South Florida buildings require an application, contractor insurance certificates and a deposit, even for work that does not need a city permit.
Can a condo association require approval before I get a building permit?
Yes. The 2026 rule that stops HOAs from requiring a permit before review applies to homeowners associations, not condominiums. Building departments may also require proof of association approval before issuing a permit.
Can I remove a wall in my condo?
Only with a permit and an engineer's confirmation that the wall is not structural and does not carry shared systems. Florida law prohibits owners from doing anything that affects the safety or soundness of the building, and walls into common areas are not the owner's to move.
Can my condo board refuse impact windows?
Not if they meet the building's hurricane protection specifications. Florida requires residential condo boards to adopt those specifications, and the board cannot refuse a conforming installation, although it can require a uniform exterior appearance.
Does the $7,500 permit exemption apply to condo units?
No. The 2026 state exemption for small jobs applies to owners of single-family homes. Condo unit work follows the normal permit rules of your city or county.

Sources

This article is general information, not legal advice. Building departments in Miami-Dade, Broward and Palm Beach counties set their own procedures, so confirm the requirements for your property with your local building department.

Scott Rosenberg

Florida Certified General Contractor, CGC1541479

Scott qualifies Rosemont Ventures Group LLC and has worked in general contracting since 1998. He writes Building Blocks to answer the questions South Florida owners ask before they build. Verify the license.

Free estimate

Tell us what you want to build

Send a few details and a licensed contractor will call you back, usually within one business day. We'll talk through scope, permits and a realistic budget range. No pressure and no obligation.

Request a callback