Got a Stop Work Order in South Florida? What the Red Tag Means and How to Get the Job Moving Again

By Scott Rosenberg, licensed GC8 min read

The short answer

A stop work order is a written order from the building official, and in Broward also the fire chief, telling everyone to stop the cited work immediately because it's being done without a required permit, beyond what the permit covers, without required inspections, by an unlicensed contractor, or in an unsafe way. The order has to state the reason and what's needed to correct it. Continuing the cited work after the order is served is a separate violation, with one exception: work the order requires to fix the violation or the unsafe condition. To get it lifted, find out exactly which department issued it and why, get the missing permit or approval (often with plans, an engineer's letter or opened walls for inspection), pay any added fee for work started without a permit, pass the inspections, and wait for the building department to release the order before anyone goes back to work. In Broward, the added fee can be up to 100 percent of the usual permit fee; in the City of Miami it's two times the fee schedule for homestead properties and four times for others, plus a base fee.

Nobody forgets the first time they see one. A bright notice taped to the front door or stapled to the fence, the crew packing up, and a phone that won't stop ringing. A stop work order feels like the end of the project. It almost never is. It's a pause with a list of conditions, and the faster you deal with those conditions, the shorter the pause.

Here's what the order actually means under Florida's building code, why they get issued in South Florida, and the order of steps that gets a job moving again.

What a stop work order is, legally

The Florida Building Code gives the building official authority to issue a stop work order whenever work regulated by the code is being done contrary to the code, or in a dangerous or unsafe way. Broward County's administrative provisions for the current code, which apply in every Broward city, spell it out:

  • Who can issue it. The building official or the fire chief.
  • How it's served. In writing, to the owner, the owner's agent or the person doing the work, or posted somewhere conspicuous on the job site.
  • What it must say. The reason for the order and the work required to correct the violation or unsafe condition.
  • What happens next. The cited work has to stop immediately.
  • If you keep going. Anyone who continues the work after being served is subject to penalties, except for work required to correct the violation or the unsafe condition.

That last point matters. The order isn't a ban on touching the property. If the inspector requires you to shore up a wall or make an electrical hazard safe, that work is allowed. Everything else waits.

The first 24 hours

  1. Stop the cited work, all of it. Not "just finish the drywall." Covering up work that hasn't been inspected is how a small problem becomes opening walls back up.
  2. Leave the notice where it was posted. Take photos of it and of the work as it stands.
  3. Find out who issued it. In Miami-Dade, a property in a city answers to that city's building department, and one in unincorporated Miami-Dade answers to the county. In Broward, most cities have their own building department, and the county's building division covers the unincorporated areas. The notice should name the department and give a case or permit number.
  4. Read the reason, then call. Ask the inspector or the department exactly what they need to release the order: a permit, revised plans, an engineer's letter, a licensed contractor of record, or an inspection of work already covered.
  5. Talk to your contractor, in writing. If the contractor caused it, your contract should say who pays to fix it. Our remodeling contract checklist covers what that clause should look like.

The most common reasons, and the fix for each

Why stop work orders get issued in South Florida, and what usually clears them
ReasonWhat usually clears it
Work without a permitApply for the permit, often with drawings, pay the added fee for starting without one, and expose any covered work for inspection
Work beyond the permit's scopeSubmit a revision or a separate permit for the added work, such as a wall that came down or a window opening that got bigger
Work that doesn't match the approved plansRevise the plans to match what was built, if an engineer can certify it, or rebuild to the approved plans
Skipped or failed inspectionsUncover the work, correct the inspector's comments and pass the inspection that was missed
Unlicensed contractorA licensed contractor takes over the permit, or the owner qualifies as owner-builder where that's allowed, and the work gets inspected
Expired permitRenew or reissue the permit and get the remaining inspections
Unsafe conditionMake it safe first, under the inspector's direction, then deal with the permit
Each department sets its own requirements for releasing an order. Use this as a starting point and confirm with the inspector named on the notice.

If you need to know whether a job needed a permit in the first place, our guide to whether you need a permit goes room by room. The 2026 exemption for single-family work under $7,500 doesn't cover electrical, plumbing, mechanical, gas or structural work, and it doesn't make an existing order go away.

What it costs: the added fee for work without a permit

The building code lets local governments charge an extra fee when work starts before the permit is issued, on top of the regular permit fee. In South Florida, the amount depends on where the property is:

Added fees for work started without a permit, examples
WhereThe added fee
Broward County and its citiesA penalty of up to 100 percent of the usual permit fee, added to the permit fees, under Broward's administrative provisions
City of MiamiTwo times the fee schedule plus a base fee for homestead properties; four times the fee schedule plus a base fee for non-homestead and commercial properties
From the Broward County Administrative Provisions for the 2023 Florida Building Code and the City of Miami building permit fee schedule (Sec. 10-18). Other cities set their own amounts, and fines from code enforcement can be separate from permit fees.

Emergency work is treated differently. If a delay would have put life or property in imminent danger, such as a burst pipe or storm damage, the work can start first, but the permit has to be applied for quickly. The City of Miami, for example, waives the added fee for emergency work if the permit is obtained within three business days. Our post on storm damage repairs covers what counts.

Why you should never just keep working

It's tempting, especially when the crew is on site and the end is close. Don't. Continuing cited work after the order is served is its own violation. Under Broward's provisions, each day a code violation continues can be treated as a separate offense, with fines and possible criminal penalties. Work that gets covered without inspection usually has to be opened back up, which costs more than the delay you were trying to avoid. And an unresolved order stays on the property's record, which shows up later when you refinance or sell, as our post on buying or selling with unpermitted work explains.

When the problem is the contractor

A lot of stop work orders in South Florida start with a contractor who didn't pull a permit, or who isn't licensed for the work. If that's your situation:

  • Check the license on the state's DBPR website. If the person isn't licensed, the Florida Department of Business and Professional Regulation can issue a cease and desist and fine unlicensed activity up to $5,000 per incident.
  • Get a licensed contractor of record. A licensed contractor can take over the job, apply for the permit, and take responsibility for the inspections. Expect them to want the work they didn't build opened up and checked before they put their license on it.
  • Don't pay more until it's sorted out. Payments to an unlicensed contractor are hard to recover, and Florida's lien law still protects the subs and suppliers who weren't paid. Our guide to construction liens explains how to avoid paying twice.
  • Read up before the next hire. Our guide to hiring a contractor has the checklist, and our demolition division's page on the risks of unlicensed contractors covers what goes wrong.

How long it takes to lift

There's no standard clock. A missed inspection can be cleared in days. Work without a permit that needs drawings, engineering and opened walls can take weeks or months, because the permit itself has to go through review. Our post on how long permits take covers the review times. The fastest path is always the same: find out exactly what the department wants, give them all of it at once, and don't restart until the order is formally released.

The bottom line

A stop work order is a list of conditions, not a verdict. Stop the cited work, leave the notice up, find out exactly what the department needs, get the permit or the fix, pay the added fee if there is one, pass the inspections and wait for the release. If your job has been red-tagged and you need a licensed contractor to take over the permit and get it moving, we do that across Miami-Dade, Broward and Palm Beach, and you can read how we work first. Tell us what happened.

Quick questions

What is a stop work order in Florida?
A written order from the building official, and in Broward also the fire chief, telling everyone to stop the cited work because it's being done contrary to the building code or in an unsafe way. It has to state the reason and what's needed to correct it, and the cited work has to stop immediately.
Can I keep working after a stop work order?
Only on work the order requires to correct the violation or an unsafe condition. Continuing any other cited work after the order is served is a separate violation and can bring fines, and covered work usually has to be opened back up for inspection.
How much is the penalty for work without a permit in South Florida?
It depends on the city. Broward's administrative provisions allow a penalty of up to 100 percent of the usual permit fee on top of the permit fees. The City of Miami charges two times the fee schedule plus a base fee for homestead properties and four times plus a base fee for others. Code enforcement fines can be separate.
How do I get a stop work order lifted?
Find out which department issued it and exactly what it needs, get the missing permit or approval, pay any added fee, correct the work and pass the required inspections, then wait for the department to formally release the order before restarting.
My contractor caused the stop work order. Who pays?
Your contract should say. If the contractor failed to pull a permit or did work beyond its scope, the cost of fixing it is usually a contract issue between you and the contractor. If the contractor isn't licensed, you can report it to the Florida DBPR, and you'll need a licensed contractor to take over the permit.
Does the $7,500 permit exemption cancel a stop work order?
No. The 2026 exemption covers some single-family work under $7,500, but not electrical, plumbing, mechanical, gas or structural work, and it doesn't release an order that's already been issued. Ask the building department what it needs.

Sources

This article is general information, not legal advice. Building departments in Miami-Dade, Broward and Palm Beach counties set their own procedures, so confirm the requirements for your property with your local building department.

Scott Rosenberg

Florida Certified General Contractor, CGC1541479

Scott qualifies Rosemont Ventures Group LLC and has worked in general contracting since 1998. He writes Building Blocks to answer the questions South Florida owners ask before they build. Verify the license.