Fixed Price, Cost Plus, Unit Price or Per Square Foot? How Contractors Price Jobs in Florida

By Scott Rosenberg, licensed GC13 min read

The short answer

Florida's building contractor exam tests four contract types: lump sum, cost plus, guaranteed maximum price and unit cost. Contractors also use time and materials for small or emergency work, and square foot pricing as a quick estimating method. The difference that matters is who carries the risk when costs change. With a lump sum (fixed price), the builder carries it, so the price includes a cushion for unknowns. With cost plus, you carry it, and you pay actual costs plus a fee, which works when the scope can't be known up front. A guaranteed maximum price caps your cost plus job. Unit pricing pays for measured quantities, which suits concrete repair and site work. Time and materials has no ceiling unless you write one in. Price per square foot is good for a ballpark and bad for a contract. Under every method, Florida law sets the same protections: deposit rules in s. 489.126, the duty to pay subs and suppliers in s. 713.345, and lien releases.

Two contractors can look at the same job, agree on the work, and hand you prices that are far apart. Sometimes one of them is wrong. More often they're pricing it differently: one is selling you a fixed number with a cushion built in, the other is selling you actual cost plus a fee, and a third is quoting a square foot figure that leaves half the job out. Until you know which method you're looking at, you can't compare the numbers.

This is something every Florida contractor has to learn before getting licensed. The building contractor exam's contract administration section tests lump sum, cost-plus, guaranteed maximum price and unit cost contracts, plus estimating from take-offs and square foot estimating, and the Florida Contractors Manual that applicants study for the business and finance exam covers contracts too. What the books can't give you is how each method plays out on a 1950s block house in Hollywood or a condo with spalling concrete. That's what this guide adds, from the homeowner's side and the builder's.

The pricing methods at a glance

Construction pricing methods and who carries the risk
MethodWho carries cost riskWorks best for
Lump sum (fixed price)BuilderComplete plans, known conditions
Cost plus percentageOwnerUnknown scope, trusted builder
Cost plus fixed feeOwner, fee fixedUnknown scope, owner wants aligned incentives
Guaranteed maximum price (GMP)Shared, capped for ownerLarger custom homes and commercial jobs
Unit priceShared: owner takes quantity, builder takes unit costConcrete repair, site work, demolition
Time and materialsOwnerSmall jobs, emergencies, investigation
Price per square footNobody, it's an estimateEarly budgeting only
Allowances aren't a separate method. They're placeholders inside a fixed-price contract, covered below.

Lump sum (fixed price)

One price for a defined scope. If the job costs the builder more than expected, the builder eats it. If it costs less, the builder keeps the difference. It's the most common way residential remodeling is sold, and the one most homeowners assume they're getting.

For the homeowner

  • Advantage: you know the number before you start, which is what lenders, insurers and your own budget want.
  • Advantage: you don't have to review receipts or manage the builder's costs.
  • Disadvantage: the price includes a contingency for risks that may never happen, and you pay it either way.
  • Disadvantage: "fixed" only covers what's written. Anything missing from the scope becomes a change order, and that's where most fixed-price fights start.

For the builder

  • Advantage: efficient work and good buying turn into profit the builder keeps.
  • Advantage: simple billing, usually by milestones.
  • Disadvantage: one bad surprise, like rotted framing, a collapsed cast iron line or a material price spike, can wipe out the margin.
  • Disadvantage: it only works with complete plans. Bidding a fixed price off a rough sketch is gambling.

Allowances: the soft spot in a fixed price

An allowance is a budget line inside a fixed-price contract for something not chosen yet: tile, plumbing fixtures, cabinets, lighting. If you pick something that costs more than the allowance, you pay the difference. If you pick something cheaper, you should get a credit.

  • For the homeowner, allowances let the job start before every finish is picked. The risk is a low allowance that makes a bid look cheaper than it really is. Ask what the allowance actually buys at a real supplier.
  • For the builder, allowances keep the price honest without forcing every decision up front. The risk is a client who hears "allowance" as "included" and is surprised by the overage.
  • Get it in writing: what each allowance covers (material only, or material and labor), whether markup applies to overages, and how credits are handled.

Used well, allowances cover the conditions nobody can see before demolition, with written change orders when an allowance is exceeded. That keeps the fixed price fixed for everything that can be known, and puts a clear rule on everything that can't.

Cost plus: percentage fee, fixed fee and GMP

You pay the builder's actual costs (labor, materials, subcontractors and the agreed job costs) plus a fee. The books are open: you see invoices, receipts and payroll. There are three common versions, and the differences are big.

  • Cost plus a percentage. The fee is a percentage of cost. Simple, but the more the job costs, the more the builder earns, which is the wrong incentive.
  • Cost plus a fixed fee. The fee is a set dollar amount. The builder's profit doesn't grow with spending, so the incentives line up better. Scope changes usually adjust the fee.
  • Guaranteed maximum price (GMP). Cost plus fee, with a ceiling. Above the GMP, the builder pays. Many GMP contracts split any savings under the cap, which rewards the builder for coming in low.

For the homeowner

  • Advantage: you don't pay for a contingency that never gets used. If the job goes smoothly, you keep the savings.
  • Advantage: you see where every dollar goes, and you can make changes without renegotiating a lump sum.
  • Disadvantage: without a GMP, there's no ceiling. Overruns, slow crews and price increases are yours.
  • Disadvantage: it takes work. You or someone you trust has to review the costs.

For the builder

  • Advantage: the margin is protected when the scope is uncertain, so the builder doesn't have to pad the price.
  • Advantage: work can start before the design is final, which matters on fast-track and emergency jobs.
  • Disadvantage: open-book accounting has to be clean and documented. Sloppy records turn into disputes, and a GMP adds real risk on top.
  • Disadvantage: the fee is often lower than the profit a well-run fixed-price job would earn.

The cost plus contract has to define "cost." Is the builder's own supervision a cost or part of the fee? Office overhead? Equipment the builder owns? Insurance and permits? Warranty work after completion? Most cost plus disputes aren't about the fee. They're about what got billed as cost.

How we price construction work

For construction and remodeling, we work cost plus whenever we can. Most of our jobs are renovations and rehabs of older South Florida houses, where nobody knows what's behind the walls until they're open, and cost plus is the honest way to price that. It only works if the books are really open, so here's how we run it:

  • Our costs are open. You see the actual invoices, receipts and subcontractor bills behind every charge, not a summary.
  • Discounts go to you. Any contractor pricing, volume discount or supplier credit we get on your job is passed on to you in full.
  • Your contractor is welcome. If you'd rather use your own contractor for a trade or part of the job, we'll accommodate it and coordinate them into the schedule. For permitted work, they'll need the right license and insurance for that trade.

Demolition is the exception. There, the debris volume can be measured up front, so our demolition division turns that take-off into a firm price, as explained in the unit price section below.

Unit price

The builder sets a price per unit (per square foot of concrete repair, per cubic yard of fill, per linear foot of pipe, per container of debris) and you pay for the quantity actually installed or removed. The builder takes the risk on the unit cost; you take the risk on the quantity.

  • For the homeowner or association: you pay for what's really there, not a guess padded for the worst case. The disadvantage is that the final total isn't known until the work is done, and quantities have to be measured and verified.
  • For the builder: no penalty for quantities nobody could see, and a clean way to price repetitive work. The disadvantage is that if the unit price is wrong, it's wrong on every unit.

Unit pricing is standard for condo concrete restoration, because the amount of spalled concrete isn't known until it's chipped out. The engineer verifies the quantities, and the association pays for the repairs actually made. Our post on condo milestone inspection repairs walks through how that works.

Time and materials

You pay hourly rates for labor plus materials, usually with a markup. It's cost plus in its simplest form, and it's the right tool for small, undefined or urgent work: tracing a leak, emergency dry-in after a storm, opening a wall to see what's inside.

  • For the homeowner: work starts right away with no long estimate. The disadvantage is the highest cost risk of any method, with no ceiling and no reward for speed. Put a not-to-exceed amount in writing.
  • For the builder: no risk on scope, paid for every hour. The disadvantage is that clients get nervous with open-ended bills, so daily time sheets and photos are what keep trust.

After a flood like the one Broward had in November, the first days of work are usually exactly this: water extraction, cutting wet drywall and making the house safe before anyone could write a scope. Once the damage is visible, the rebuild can move to a fixed price. Our Broward flood repair permits post covers the permit side of that switch.

Price per square foot: an estimate, not a contract

Square foot pricing is the first number everyone asks for, and it has a real use: early budgeting. Florida's exam treats it as an estimating method, not a contract type, and that's the right way to think about it. A square foot number takes a typical project and spreads its cost over the floor area.

  • For the homeowner: it answers "can I afford this at all?" in seconds. The disadvantage is that it hides what actually moves the price: the lot, the flood zone, impact windows, the roof, site work, permits and finishes. Two houses of the same size can be very different jobs.
  • For the builder: it's a quick way to qualify a lead. The disadvantage is that a square foot number quoted too early becomes the number the client remembers, and every honest line item after that looks like an increase.

If a contractor quotes per square foot, ask what's excluded. Our guide to the cost to build a house in South Florida explains why per square foot figures for new construction leave out so much here.

How to choose the right method

  1. How complete are the plans? Complete drawings and known conditions point to a lump sum. A rough idea or unknown conditions point to cost plus, unit price or a phased approach.
  2. How much can be seen before work starts? Old houses, water damage and concrete repair hide their real condition. Pay for what's found, not for a guess.
  3. How much do you want to be involved? Cost plus takes time to review. A lump sum takes time up front to define the scope.
  4. Can you combine methods? Often the best answer is a mix: time and materials to investigate, then a fixed price once the scope is known, with allowances or unit prices for the parts that stay uncertain.

Florida protections that apply under every method

  • Deposits. Under Florida Statute 489.126, a contractor who takes more than 10 percent of the contract price as a first payment on residential work must apply for permits within 30 days and start work within 90 days after the permits are issued, unless there's just cause or you agreed in writing to a longer period.
  • Paying ahead of the work. The same statute makes it prima facie evidence of a problem when a contractor has been paid more than the value of the work done and doesn't work for 90 days without just cause.
  • Your money goes to your job. Florida Statute 713.345 requires a contractor to use your payments to pay the labor and materials already supplied to your project. Knowingly misapplying those funds is a felony. This matters most in cost plus, where you're paying the builder's invoices directly.
  • Liens. Under any method, unpaid subs and suppliers can lien your house. Ask for lien releases with each payment, as our lien law guide explains.
  • Required notices. A Florida residential contract over $2,500 needs the lien law notice and the Homeowners' Construction Recovery Fund notice. Our contract checklist lists the rest.

Whatever the method, the protection is the same: a written scope, a clear definition of what's in the price, a payment schedule tied to work actually done, and change orders signed before the extra work starts. If you're comparing bids that use different methods, we're happy to look at them with you. Tell us about your project.

Quick questions

What is the difference between a fixed price and a cost plus contract?
With a fixed price (lump sum), the builder agrees to one price for a defined scope and carries the risk if costs go up. With cost plus, you pay the builder's actual costs plus a fee, so you carry the risk but also keep the savings. Fixed price suits complete plans and known conditions; cost plus suits jobs where the scope can't be known up front.
Is cost plus a good idea for a homeowner?
It can be, with the right builder and the right contract. Cost plus avoids paying for a contingency that never gets used, but without a cap there's no ceiling on what you spend. A fixed fee instead of a percentage, a clear definition of what counts as cost, open books and a guaranteed maximum price make it much safer.
How does Rosemont Ventures Group price construction jobs?
For construction and remodeling we work cost plus whenever we can, with open books: you see the real invoices, all contractor and supplier discounts are passed on to you, and if you prefer your own contractor for a trade, we'll accommodate them. Demolition is priced differently, as a firm number from a measured take-off of the debris.
What is a guaranteed maximum price contract?
A guaranteed maximum price (GMP) contract is cost plus a fee with a ceiling. You pay actual costs plus the fee up to the GMP, and the builder pays anything above it. Many GMP contracts share any savings under the cap between the owner and the builder.
What is unit price contracting?
The builder sets a price per unit, such as per square foot of concrete repair or per cubic yard of fill, and you pay for the quantity actually done. It's common for condo concrete restoration and site work, where quantities aren't known until the work is opened up.
Should I hire a contractor who quotes per square foot?
A per square foot number is fine for early budgeting, but don't sign a contract on it. Ask what it excludes, since site work, permits, impact windows, the roof and finishes often aren't in it. A real price comes from a take-off of the actual job.
How much deposit can a contractor take in Florida?
Florida doesn't cap the deposit, but under s. 489.126 a contractor who takes more than 10 percent of the contract price as a first payment on residential work must apply for permits within 30 days and start within 90 days after the permits are issued, unless there's just cause or you agreed in writing to a longer period.
What is an allowance in a construction contract?
An allowance is a budget line in a fixed-price contract for something not chosen yet, like tile or fixtures. If your choice costs more, you pay the difference; if it costs less, you should get a credit. The contract should say what each allowance covers and how overages are marked up.

Sources

This article is general information, not legal advice. Building departments in Miami-Dade, Broward and Palm Beach counties set their own procedures, so confirm the requirements for your property with your local building department.

Scott Rosenberg

Florida Certified General Contractor, CGC1541479

Scott qualifies Rosemont Ventures Group LLC and has worked in general contracting since 1998. He writes Building Blocks to answer the questions South Florida owners ask before they build. Verify the license.

Free estimate

Tell us what you want to build

Send a few details and a licensed contractor will call you back, usually within one business day. We'll talk through scope, permits and a realistic budget range. No pressure and no obligation.

Request a callback